Epoch: Huawei Horinger ≈ 7% of Colossus 2
Partly confirmed
The takeaway
A new building due in early 2028 would raise it to ~141,000 H100e, while Colossus 2 is expected to reach 1.8M+.
Status
- Claim
Partly confirmed
- Our reporting
- Medium confidence
- Importance
- 3 of 5
- Last verified
- 16 November 2026
Your AI and this story
- GPT-6.2 Astra165 days after its cutoff
- Claude Opus 5.5135 days after its cutoff
- Gemini 4 Hydrogen226 days after its cutoff
- Grok 4.7165 days after its cutoff
None of these four assistants can know about it. The closest, Claude Opus 5.5, stops 135 days before it.
Key facts
- Method: satellite images of Aug 18, 2026; cooling towers and chillers counted to model heat rejection, then IT power and chip counts, cross-checked with chip-sales estimates (four-month lag) and Huawei disclosures; operation inferred from water vapour and moving fans
- Campus: three zones; six buildings, four with dense cooling (~286 MW IT); the North zone has few cooling towers and probably no powerful AI chips
- Compute: ~81,000 H100e (90% CI 36,000-141,000); Huawei’s figures put a 910C at ~0.76 H100e vs ~2.5 for Nvidia B200/B300
- Comparison: Colossus 2 (Tennessee, SpaceXAI) has ~14x Horinger’s compute and should reach at least 1.8M H100e by 2028; Huawei’s Wuhu campus is projected at 151,000 H100e by December 2027
- Epoch’s wider finding: US AI data centres get about 2.5x more AI compute per unit of power than Chinese ones; China’s compute constraints ‘are unlikely to ease in the next two years’
- Techmeme ran the analysis on Nov 16
What happened
Epoch published a condensed version of a longer satellite-based report on one of China’s largest AI campuses. Even counting all four cooled buildings as fully populated with Ascend chips, the site holds a small fraction of the compute of the largest US cluster.
Why it matters
It is one of the few independent, physical estimates of Chinese AI compute, published as US export controls tighten after the Nvidia scandal and as Chinese labs report capacity limits (DeepSeek chat limits over capacity).
Sources
1 source from 1 site. Numbers match the chips in the text.
1 source: 1 primary
Primary
- Epoch AI: What Huawei’s Horinger data center reveals about China’s compute gap (Nov 12)epochai.substack.com, official
Changes
- Filed (news agent)