Anthropic agrees to pay Nscale $45B over six years for ~460 MW at the Monarch campus in West Virginia
Confirmed
The takeaway
Bloomberg reported on Aug 26, 2026 that Anthropic agreed to spend $45B over six years renting about 460 MW of AI computing capacity from Nscale at its Monarch Compute Campus in Mason County, West Virginia, with Nvidia Vera Rubin chips coming online from late 2027.
Status
- Claim
Confirmed
- Our reporting
- High confidence
- Importance
- 3 of 5
- Last verified
- 30 October 2026
Your AI and this story
- GPT-6.2 Astra87 days after its cutoff
- Claude Opus 5.557 days after its cutoff
- Gemini 4 Hydrogen148 days after its cutoff
- Grok 4.787 days after its cutoff
None of these four assistants can know about it. The closest, Claude Opus 5.5, stops 57 days before it.
Key facts
- Deal (Bloomberg via TNW, Aug 26): ~$45B over six years, ~460 MW (roughly what 345,000 US homes draw), first of three buildings; Nvidia Vera Rubin chips from late 2027
- Campus: Monarch Compute Campus, up to 2,250 acres in Mason County, WV, acquired by Nscale in March 2026 via AIP Corp; ~1.35 GW for the first buildings, power runway above 8 GW; full campus plus on-site power plant ~$71B per planning documents, $47B of it chips (TNW)
- Microsoft signed a letter of intent for 1.35 GW in March 2026 and walked away in the summer, leaving Anthropic as tenant (TNW)
- The contract became the largest item in Nscale’s ~$103B contracted backlog ahead of its US listing (see Nscale raises $3.36B in convertible notes ahead of a planned ~$35B NYSE IPO)
- Chestnut grove (Oct 2026): about 200 blight-resistant American chestnuts planted in the 1970s at the former Clements State Tree Nursery in West Columbia, the main seed source of the American Chestnut Foundation’s WV chapter, may be cleared as early as Nov 1, 2026, per advocacy sources cited by Futurism and Gadget Review; the project’s website says the nursery is not on its land, and neither Nscale nor Anthropic had commented (unresolved)
- TACF’s WV chapter newsletter (April 2026) says it had tried for years to learn whether the trees would be affected, with no reply from the governor’s or commerce secretary’s office
- Second deal in talks (Bloomberg, Oct 19, via Investing.com): Nscale and Anthropic are negotiating another ~$45B agreement for a second Monarch building, again 460 MW of Vera Rubin capacity; it ‘could be finalized within days’ but terms may change; Anthropic reportedly holds a right of first refusal on the campus’s expected third building. Nscale’s IPO filing puts existing Anthropic agreements at up to $44.6B. Both companies declined to comment. The talks came a day after Microsoft dropped its Loughton (UK) anchor-tenant deal with Nscale
- Nvidia backstop (The Information, Oct 29, paywalled; Techmeme and Reuters summaries): Nvidia is in talks to give Nscale billions of dollars in credit guarantees for the debt to build the 460MW data centre Anthropic plans to use; the FT (Oct 29) describes the 2,250-acre, 8GW Monarch campus as hit by construction issues, local opposition and financing risks
What happened
Anthropic added another multi-year compute lease to a string of 2026 deals (SpaceX, Fluidstack, Lambda, Akamai). Nscale, a two-year-old London company, took over a West Virginia site first planned for Microsoft and booked Anthropic as its anchor tenant before going public.
Why it matters
It is one of the largest single compute contracts of 2026 and a big part of Nscale’s backlog. The chestnut grove dispute shows how local environmental concerns around AI campuses now reach the labs that rent them, even when the lab is only a tenant.
Sources
10 sources from 10 sites. Numbers match the chips in the text.
10 sources: 1 primary, 9 press
Primary
- American Chestnut Foundation, WV chapter newsletter (April 2026): Monarch Data Center in Mason Countytacf.org, official
Press
- Investing.com (Bloomberg): Nscale in talks for $45 billion Anthropic AI deal as IPO looms (Oct 19)investing.com, press
- Bloomberg: Anthropic to pay Nscale $45 billion for AI computing power (Aug 26, 2026)bloomberg.com, press
- TNW: Anthropic signs $45B compute deal with Britain’s Nscalethenextweb.com, press
- DatacenterDynamics: Anthropic signs $45bn compute capacity agreement with Nscale (report)datacenterdynamics.com, press
- Futurism: One of America’s last remaining chestnut groves could be wiped out for an AI data center (Oct 10)futurism.com, press
- Gadget Review: One of America’s last chestnut groves is about to be destroyed for a data centergadgetreview.com, press
- The Information: Nvidia moves to backstop a cloud provider’s $45 billion Anthropic project (Oct 29, paywalled)theinformation.com, press
- Reuters: Nvidia in talks to give credit support for Nscale’s deal with Anthropic (Oct 30)reuters.com, press
- FT: Inside Nscale’s Monarch Compute Campus in West Virginia (Oct 29, paywalled)ft.com, press
Changes
- Added Nvidia’s credit-guarantee talks (The Information/Reuters headlines) and the FT’s Monarch campus report (news agent; all paywalled, written from Techmeme summaries)
- Bloomberg (via Investing.com) reports talks on a second ~$45B, 460 MW deal for a second Monarch building and a right of first refusal on a third (Google News/Seeking Alpha)
- Filed as a review (the deal had only been mentioned inside the Nscale IPO entry), with the October chestnut-grove dispute (Futurism)